Identifying and Prioritizing Critical Risk Factors in the Context of a High-Voltage Power Transmission Line Construction Project: A Case Study from Sri Lanka

dc.citation.issue4
dc.citation.volume5
dc.contributor.authorWeerakkody W
dc.contributor.authorRathnayaka B
dc.contributor.authorSiriwardana C
dc.contributor.editorLuongo A
dc.contributor.editorGiunta MS
dc.date.accessioned2025-01-14T01:12:04Z
dc.date.available2025-01-14T01:12:04Z
dc.date.issued2024-12
dc.description.abstractThis study addresses critical risk factors in high-voltage power transmission line (HVPTL) construction projects, which are vital components of national energy infrastructure. HVPTL projects are essential for meeting energy needs but are often plagued by risks due to their linear construction nature, leading to project underperformance. However, the lack of attention to risk management often leads to project underperformance. This research aims to identify and rank these risks to facilitate effective risk management. Through literature review and preliminary surveys, 63 risk elements were identified under 14 main categories. These risks were ranked using two rounds of Delphi surveys and the analytical hierarchy process (AHP). The study focuses on a Sri Lankan HVPTL project. The most critical risk factors identified include “improper planning by the main contractor”, “delays in decision-making by the client/consultant”, “errors in initial costing”, and “inaccuracies in survey data”, with AHP analysis assigning significant weights of 43.9%, 18%, 16%, and 14.9% to these factors, respectively. Comparative analysis with similar studies reveals consistent findings, underscoring the importance of addressing delays in approvals, material unavailability, and construction-quality challenges. These results emphasize the necessity of adopting systematic risk-management techniques in HVPTL projects to mitigate uncertainties and enhance project outcomes.
dc.description.confidentialfalse
dc.format.pagination1057-1088
dc.identifier.citationWeerakkody W, Rathnayaka B, Siriwardana C. (2024). Identifying and Prioritizing Critical Risk Factors in the Context of a High-Voltage Power Transmission Line Construction Project: A Case Study from Sri Lanka. CivilEng. 5. 4. (pp. 1057-1088).
dc.identifier.doi10.3390/civileng5040052
dc.identifier.eissn2673-4109
dc.identifier.elements-typejournal-article
dc.identifier.urihttps://mro.massey.ac.nz/handle/10179/72367
dc.languageEnglish
dc.publisherMDPI, Basel, Switzerland
dc.publisher.urihttps://www.mdpi.com/2673-4109/5/4/52
dc.relation.isPartOfCivilEng
dc.rights(c) 2024 The Author/s
dc.rightsCC BY 4.0
dc.rights.urihttps://creativecommons.org/licenses/by/4.0/
dc.subjecthigh-voltage power transmission lines
dc.subjectDelphi survey
dc.subjectcritical risk factors
dc.subjectrisk management
dc.subjectAHP
dc.subjectconstruction
dc.titleIdentifying and Prioritizing Critical Risk Factors in the Context of a High-Voltage Power Transmission Line Construction Project: A Case Study from Sri Lanka
dc.typeJournal article
pubs.elements-id493305
pubs.organisational-groupOther

Files

Original bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
493305 PDF.pdf
Size:
11.59 MB
Format:
Adobe Portable Document Format
Description:
Published version.pdf

License bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
9.22 KB
Format:
Plain Text
Description:

Collections